Project Overview​
An overseas telecom operator was expanding its 5G network, facing challenges such as insufficient power of traditional equipment, weak monitoring, difficult expansion, unstable grid supply, and demands for green low-carbon operations and rapid deployment.​
Solution (Beijing Ding Ding Future Technology)​
  • Core Equipment Room: 48V 168KW High-power DC Power System (high-reliability redundant design)​
  • Indoor Sites: Flatpack2 48V 84KW Integrated Cabinet Power (OEM customization + rapid deployment)​
  • Edge Nodes: Eltek 24-32KW Embedded Power System (intelligent monitoring + plug-and-play)​
  • Remote Sites: Hybrid Solar Power System (solar-storage integration + cost & emission reduction)​
Core Advantages​
High Reliability: System availability ≥99.99%, ensuring uninterrupted services​
Intelligent O&M: Remote monitoring, reducing on-site inspections by 50%+​
Flexible Delivery: MOQ 1 set, customized adaptation + fast supply​
Green & Efficient: High conversion efficiency, solar solution reduces carbon emissions​
Implementation Results​
  • Significantly improved power supply stability and reduced downtime​
  • Considerable annual energy savings per site and lower O&M costs​
  • Rapidly adapted to 5G construction cycles, becoming the operator’s preferred supplier